Cornish Metals Inc. - POSITIVE PEA RESULTS FOR SOUTH CROFTY TIN PROJECT
Released
Released
Announcement PDF
RNS Number : 7092M
Cornish Metals Inc.
01 May 2024
CORNISH METALS REPORTS POSITIVE PRELIMINARY ECONOMIC ASSESSMENT RESULTS FOR
SOUTH CROFTY TIN PROJECT
Vancouver, April 30, 2024
Cornish Metals Inc. (AIM/TSX-V: CUSN) ("Cornish Metals" or the "Company"), is pleased to report
a positive independent Preliminary Economic Assessment ("PEA") for its 100% owned and
permitted South Crofty tin project ("South Crofty" or the "Project") located in Cornwall, United
Kingdom.
The PEA validates South Crofty's economic viability, producing a base case after-tax Net Present
Value ("NPV") of US$201 million and Internal Rate of Return ("IRR") of 29.8%, and confirms the
Project's potential to be a low-cost and long-life tin mining operation with a current 14-year life of
mine ("LOM"). South Crofty is expected to produce a clean, high-grade tin concentrate and to
be an important tin producer in Europe, supplying into the growing demand for this critical metal
that is essential for the energy transition.
Highlights
Ø Attractive project economics and financial metrics
· US$201 million after-tax NPV8% and 29.8% IRR at base case tin price of US$31,000 /tonne
· US$235 million after-tax NPV8% and 32.8% IRR at the current US$32,625 /tonne LME tin price
· Capital payback period of 3 years after-tax
· Total after-tax cash flow of approximately US$626 million from start of production, peaking at US$82
million in the second year of production
· Average annual earnings before interest, taxes, depreciation and amortisation ("EBITDA") of US$83 million
and 62.1% EBITDA margin in years 2 through 6
Ø Considerable tin production with upside opportunities
· 49,310 tonnes of tin metal in concentrate produced over a 14-year LOM
· Average annual tin production of over 4,700 tonnes for years 2 through 6 (~1.6% of global mined tin
production)
· Peak tin production of over 5,000 tonnes in year 4
· Average LOM processed head grade of 1.83% tin, upgraded from an average mined grade of 0.94% tin
through use of X-Ray Transmission ("XRT") ore sorting and Dynamic Dense Media Separation ("DMS")
· Growth opportunities from additional in-mine and near-mine exploration with the potential to materially
extend the mine life and increase production
Ø Permitted Project with low capital intensity and unit costs
· Pre-production capital requirement of US$177 million
· Fully permitted project with existing mine infrastructure, mining permission through 2071 and full planning
permission to construct a processing plant to recover tin concentrate
· LOM average all-in sustaining cash cost ("AISC") of US$13,661 /tonne of payable tin, positioning South
Crofty as a low cost tin producer
· Average AISC of US$12,375 /tonne of payable tin for years 2 through 6
Ø Sustainable mining operation with strong ESG credentials
· Operations will use modern, trackless, mechanised underground mining methods and latest tin processing
technologies
· Low impact underground operation with paste backfilling of process tailings into existing, historic mine
workings
· Use of 100% renewable electricity supply and exploring options for renewable power generation
· Preference for using local supply chains supporting the local economy and building on the existing
capability and knowledge still present in Cornwall
· Potential to directly employ up to 320 people with permanent high-skilled and well-paid jobs and create up
to 1,000 indirect jobs
Ø Cornish Metals will host a PEA presentation on 1 May 2024 at 3:00pm London time. Please register at:
https://www.investormeetcompany.com/cornish-metals-inc/register-investor.
Ø A technical report prepared in accordance with NI 43-101 will be filed on SEDAR+ within 45 days of this
announcement.
Ken Armstrong, Interim CEO and Director of Cornish Metals, stated: "Congratulations to
Cornish Metals' technical team on completion of this Preliminary Economic Assessment of the
South Crofty tin project. This PEA is an important milestone for Cornish Metals and our goal of
bringing responsible tin mining back to Cornwall and the United Kingdom. South Crofty is a
strategic asset as tin is recognised as a critical metal by the United Kingdom and other national
governments, while there is currently no primary tin production in Europe or North America.
Most often PEAs are completed prior to entering the mine permitting process. South Crofty has
the advantage of having already cleared these hurdles and benefits from an existing mine permit
and process plant construction permissions as well as existing mining, transportation and
renewable energy infrastructure."
Owen Mihalop, COO of Cornish Metals, stated: "The PEA results are compelling with a post-tax
NPV8% of $201 million and IRR of about 30% at a tin price of US$31,000. This represents a strong
foundation for further evaluation of the Project, enabling the Company to move forward with
additional preparation work and progress towards a construction decision, with planned first tin
production in 2027.
The low all-in sustaining cost of about US$13,700 per tonne of payable tin is an important metric
and potentially positions the project within the lowest quartile of the global tin industry cost
curve. We believe the opportunities for mineral resource expansion at South Crofty, and beyond,
are significant and this will come into focus when the current mine dewatering and shaft
refurbishment project is complete by Q3 2025, and new mineral resource definition and
exploration drilling can be undertaken in parallel with a potential construction decision for the
Project."
PEA Summary Outcomes
Operations
Mine throughput
500 ktpa
Processed throughput
250 ktpa
LOM
14 years
Capital costs
Operating
costs
Total LOM tonnes mined
5,955 kt
Average mined tin grade
0.94%
Contained tin
56,133 t
Total LOM tonnes processed
2,988 kt
Average processed tin grade
1.83%
Average tin recovery
87.8%
Total LOM tin produced
49,310 t
Total LOM copper produced
3,844 t
Total LOM zinc produced
3,225 t
Years 2-6 average annual tin production
4,728 t
Pre-production
US$177 million
Post-production
US$54 million
Average LOM net cash cost
Average LOM AISC
Economic
assumptions
Financials
US$12,705 /tonne tin payable
US$13,661 /tonne tin payable
Tin price
US$31,000 /tonne
GB£:US$
1.25
UK corporate tax rate
25%
NPV (8%) - Pre-tax / After-tax
IRR - Pre-tax / After-tax
Capital payback period After-tax
US$264 million / US$201 million
33.4% / 29.8%
3.0 years
Total LOM Revenue
US$1,563 million
Total LOM EBITDA
US$806 million
After-tax Free Cash Flow (from start of
production)
US$626 million
Years 2-6 average annual EBITDA
US$83 million
Years 2-6 average annual after-tax Free Cash
Flow
US$65 million
Table 1: South Crofty PEA operating and economic summary
Notes:
-
NPV effective as at 1 January 2025;
Pre-production capex excludes currently committed items;
Project modelled in GB£, values converted to US$ using a flat GB£:US$ rate of 1.25.
Financial modelling includes Inferred Resources.
The evaluation at a PEA level of study includes Indicated and Inferred blocks and consequently it is not possible to define
a Mineral Reserve. The PEA is preliminary in nature and includes Inferred Mineral Resources that are considered too
speculative geologically to have economic considerations applied that would enable them to be categorised as Mineral
Reserves. There is no certainty that the PEA will be realised.
Sensitivity Analysis
A sensitivity analysis was performed on the base case pre-tax NPV to examine project sensitivity
to metal prices, capital and operating costs, grades and process recoveries.
Figure 1: Pre-tax NPV8% sensitivity analysis to various project parameters
South Crofty Project economics are well supported at a range of tin price assumptions and
discount rates. The PEA base-case tin price of US$31,000 /tonne provided by Project Blue, a global
consultancy that provides market intelligence on critical materials for the energy transition,
reflects anticipated supply shortfalls that will drive the market into a deficit from later this decade.
After-tax NPV
(US$M)
Discount
Rate
5%
6%
8%
10%
12%
-20%
Commodity Price
-10%
0%
+10%
120
196
272
348
424
105
175
246
317
387
78
139
201
263
325
55
110
164
218
272
37
85
133
181
229
+20%
Table 2: Metal price and discount rate sensitivity analysis
Note: Base case prices used - tin: US$31,000/t, copper: US$8,500/t, zinc: US$2,500/t
Project Description
South Crofty is a former producing tin mine located in the historic central tin mining district of
Cornwall, United Kingdom. The current Project comprises the former producing South Crofty and
Dolcoath mines, which were two of the most significant mines in the Cornish tin mining district.
South Crofty has over 400 years of operational history until its closure in March 1998. The Project
is wholly owned by Cornish Metals.
Figure 2: South Crofty Project location
South Crofty was granted surface and underground development planning permissions by
Cornwall Council, the Local Planning Authority, in 2011 and 2013. The underground mining
permissions are valid until 2071 and cover a project area of 1,490 hectares with a working depth
of 1,500 metres below surface. Cornish Metals also has approximately 7.65 ha (18.9 acres) of
surface ownership that include the area covered by surface planning permission to construct a
processing plant facility.
Current infrastructure at South Crofty will help support any future development of the Project and
includes office and warehouse buildings, the partially refurbished New Cooks Kitchen ("NCK")
shaft, a recently built and commissioned water treatment plant and a modern decline that extends
to a depth of 120 metres. NCK shaft is one of the five usable main shafts serving the mine
workings, and historically was the main service and hoisting shaft. More recent infrastructure
advancements, including the ongoing refurbishment and servicing of shafts and construction and
operation of the mine water treatment plant, have been implemented to support access into the
historical mine. Refurbishment of NCK shaft will significantly improve functionality of the shaft,
enable larger equipment to access the mine at an earlier stage in its re-development and ensure
continued safe operations as access to underground mine workings is regained.
The Project site has excellent transportation and power infrastructure, including the A30 trunk
road located less than 1 km to the north and the national railway line that borders the site to the
south. There are modern active port facilities at Falmouth approximately 17 km to the south-east.
The Project is located within an industrial area with highly developed power supply and regional
distribution, with two 33 kV overhead power lines which cross the Project area, and a dedicated
11 kV power supply to NCK shaft.
Economic Benefits to the UK and Local Communities
Cornwall has a strong history of mining with significant mining capability and knowledge still
present in the local workforce. With a local urban population of approximately 59,000, there are
sufficient local human resources to staff many skilled, unskilled, or partially skilled jobs at a mine.
The PEA indicates that development of South Crofty could provide substantial economic benefits
at the local and national levels, including:
· During the pre-production mine development period, the Project is anticipated to generate approximately
175 direct jobs, and additional employment through contracted construction of surface and underground
facilities;
· During operations, the mine is expected to directly employ up to 320 people with permanent high-skilled
and well-paid jobs;
· The Project has potential to generate up to 1,000 indirect jobs with local and national contractors and
suppliers of products and services;
· Using a base case tin price of US$31,000 per tonne, the Project is estimated to pay total UK corporation
taxes of £102 million (approximately US$127 million) over the LOM. Additional government revenue will
be generated by employee income tax and national insurance contributions;
· The Company will provide full training and skills development where necessary in order to maximise
employment of local residents at the Project;
· Environmental benefits through the ongoing treatment of the South Crofty mine water being discharged
into the Red River, having a positive effect on the quality of the river downstream of the discharge point.
Mineral Resource & Mineralised Material Mined
The Mineral Resource at South Crofty is divided into two areas: the Upper Mine Mineral Resource,
which is predominantly polymetallic tin-copper-zinc mineralisation hosted in metasedimentary
country rock, and the much more substantial Lower Mine Mineral Resource which is tin-only and
hosted predominantly in granite.
Figure 3: Plan view of South Crofty Resource
Note: Lower Mine (orange), Upper Mine (turquoise), mine development (purple), and the surface decline (green)
The PEA indicates that approximately 6 million tonnes of mineralised material, at an average
grade of 0.97% SnEq, is amenable to mining, and is based on the NI 43-101 & JORC (2012)
compliant Mineral Resource Estimate ("MRE") published by Cornish Metals in October 2023 as
detailed below:
South Crofty Summary (JORC 2012) Mineral Resource Estimate
Contained Tin /
Tin Equivalent
(kt)
Classification
Mass
(kt)
Grade
Lower
Mine
Indicated
2,896
1.50% Sn
43.6
Inferred
2,626
1.42% Sn
37.4
Upper
Mine
Indicated
260
0.99% SnEq
2.6
Inferred
465
0.91% SnEq
4.2
Area
Table 3: South Crofty Mineral Resource summary
Notes:
1.
The Mineral Resource estimate is reported in accordance with the requirements of the Joint Ore Reserves Committee of
the Australian Institute of Mining and Metallurgy, the JORC Code (2012).
2.
The Qualified Person for this Mineral Resource Estimate is: Mr Nicholas Szebor, MCSM, MSc, BSc, CGeol, EurGeol, FGS, of
AMC Consultants (UK) Ltd.
3.
Mineral Resources for the Lower Mine are estimated by conventional block modelling based on wireframing at 0.4% Sn
threshold whilst honouring lode continuity and by ordinary kriging or inverse distance to the power of 3 grade
interpolation.
4.
Mineral Resources for the Upper Mine are estimated by conventional 3D block modelling based on wireframing at 0.5%
SnEq cut-off grade and a minimum width of 1.2m and estimated by inverse distance to the power of 3 grade interpolation.
5.
SnEq is calculated using the formula: SnEq% = Sn% + (Cu% x 0.314) + (Zn% x 0.087). Cornish Metals has used metal prices of
US$24,500/Tonne Sn, US$8,000/Tonne Cu, and US$2,700/Tonne Zn. Assumptions for process recovery are 88.5% for Sn, 85%
for Cu and 70% for Zn.
6.
Cut-off grade was calculated assuming a 24,500 $/t tin price and an assumed metal recovery of 88.5%
7.
For the purpose of this Mineral Resource Estimate, assays were capped by lode for the "Lower Mine" between 1.5% Sn
and 23% Sn and for the "Upper Mine" at 6% for Sn, 4% for Cu, and 20% for Zn.
8.
Bulk densities of 2.77 t/m3 and 3.00 t/m3 have been applied for volume to tonnes conversion for the granite hosted and
metasediment (Killas) hosted Mineral Resources respectively.
9.
Mineral Resources for the Lower Mine have had a minimum mining width of 1.2m applied using 0% Sn dilution. A 1.2m
mining width was applied to the Upper Mine during wireframing.
10.
Mineral Resources are for the Upper Mine are estimated from near surface to a depth of approximately 350m and for the
Lower Mine from a depth of approximately 350m to a depth of approximately 870m.
11.
Mineral Resources are classified as Indicated and Inferred based on drillhole and channel sample distribution and density,
interpreted geological continuity and quality of data.
12.
The Mineral Resources have been depleted for past mining, however, they contain portions that may not be recoverable
pending further engineering studies.
13.
Mineral Resources which are not Mineral Reserves do not have demonstrated economic viability. The estimate of Mineral
Resources may be materially affected by environmental, permitting, legal, title, taxation, socio-political, marketing, or other
relevant issues.
14.
Effective date 6th September 2023.
15.
Numbers may not compute exactly due to rounding.
Mining Methods
The South Crofty mine will be accessed via the NCK shaft, which will provide initial access to the
existing mine levels and new stoping areas. NCK shaft will serve as primary access to the mine for
personnel and materials as well as hoisting of material for transfer to the processing plant, which
will be located adjacent to the decline.
The mine design will utilise existing development where possible, which will be rehabilitated or
slashed for larger equipment, to access production areas. New internal ramps will be developed
providing mechanised access to other levels. The ramps are driven at -15% grade and 4.0 metres
wide by 4.0 metres high to allow for truck access, ventilation and services. Sections of levels to be
used for services distribution and ventilation will only require rehabilitation. Lateral access drives
will be mined from slashed levels, haulage ramps and access ramps to stopes and stope access
development. Areas that are being utilised for ventilation, services or limited access will be
rehabilitated only.
Annual mined material of up to approximately 500,000 tonnes (~1,370 tonnes per day) is planned
with longhole stoping mining methods selected. Sub-level longhole stoping is the main mining
method and is well suited given the excellent ground conditions, average stope dip of 70 degrees,
continuity along strike and vertically for at least 20 metres. The method also allows for selectivity
of mining where required.
The mine generally consists of blocks of stopes separated by regions of lower grade material
and/or historical workings. Mining direction is generally extracted in a top-down sequence,
retreating along access.
Figure 4: Mining design (isometric long section looking west)
Process Plant
The historic Wheal Jane Concentrator, incorporating key metallurgical improvements made
between 1991 and 1998 as well as results from the Company's 2023 metallurgical test
programme, was utilised as the basis for developing the process plant flowsheet including
incorporation of a pre-concentration plant. The pre-concentration plant consists of XRT ore sorting
and DMS for all +0.85mm material, with fines reporting downstream without pre-concentration.
Pre-concentration reduces the size and cost of the downstream concentrator considerably and
draws on the strengths of both pre-concentration technologies, XRT being more effective on
coarser size fractions and DMS on the finer size fractions.
The 2023 metallurgical test programme tested the suitability of XRT pre-concentration and DMS
and provided representative material to verify historic production records, operating data and
flowsheet. The process plant will include:
·
Underground primary single stage crushing;
·
Two stage secondary crushing and XRT / DMS separation;
·
Tertiary crushing of XRT products to produce nominal -15mm material for grinding;
·
Open circuit rod mill followed by closed circuit ball mill with screens;
·
Provision for a flotation section to process polymetallic material from year 4 onwards;
·
Classification and primary gravity concentration using a combination of shaking tables and
Multi Gravity Separation ("MGS");
·
Regrinding of primary gravity tailings followed by secondary gravity concentration using a
combination of shaking tables and MGS;
·
Tertiary ultrafine gravity separation using a combination of Falcon "Continuous"
Concentrators and MGS, and;
·
Tin Dressing to remove sulphides from gravity concentrates and filter the final product for
shipment for smelting.
Figure 5: South Crofty conceptual process plant layout and external design
Mine Backfill
South Crofty will be a low impact underground mining operation with no surface tailings storage.
Process tailings will be backfilled as a paste into existing void spaces left by historic mining.
The South Crofty tailings material is a typical gravity/floatation processing product. The proportion
of fines and material size range means that the whole tailings stream is suitable for paste backfill
with samples achieving suitable strength and target densities for reticulation.
The backfill plant has been designed and sized to meet the requirements of the mine with the
intent of filling existing void space from previous mining prior to filling new mining voids created
by current operations. In-cycle backfill is not required, and there is no requirement to undercut
paste backfilled areas in the current mine plan.
The mine production is estimated to produce approximately 2.2 million cubic metres of paste
backfill over the LOM.
The backfill plant will be located adjacent to the water treatment plant and the process plant to
allow for shared services and simplified operations. The backfill plant consists of four main
sections: an external thickened tailings receiving tank; filtration equipment; the cement handling
system; and the mixing system.
Figure 6: South Crofty conceptual backfill plant design.
Production Profile
The production profile at South Crofty is based on annual throughput of approximately 500,000
tonnes and annual processing of approximately 250,000 tonnes at an average tin grade of 1.83%
(1.88% tin-equivalent). LOM tin production is expected to total 49,310 tonnes (50,320 tonnes of
tin-equivalent), averaging over 4,700 tonnes of tin per year in the first five years post ramp-up
(years 2 to 6) and peaking at over 5,000 tonnes in year 4.
Figure 7: South Crofty indicative production profile
The use of pre-concentration through XRT and DMS at the front end of the processing plant
materially reduces the volume of material processed and required for backfilling to approximately
half of the material mined. The impact to grades is also significant, with LOM processed tin grades
averaging 1.83%, almost double the average mined grade of 0.94% tin. Processed tin grades in
years two through six average above 2%.
Figure 8: South Crofty mined and processed tin grades
Capital and Operating Costs
The pre-production capital cost of the South Crofty project is estimated to be US$177 million. The
LOM sustaining capital is estimated to be a further US$54 million, comprising mine capital
development, a process plant upgrade for polymetallic material in the fourth year from start of
production and processing plant sustaining capex.
(US$M)
Mine development, equipment and pre-production
Mine capitalised operating costs
Process plant
NCK Shaft refurbishment (east side) and underground infrastructure
Phase 2 winders purchase and installation
Other surface infrastructure
Paste backfill plant
Owners G&A cost
Contingency @ 15% (20% for process plant)
Total
9.2
40.5
59.7
12.3
3.9
6.9
13.2
5.8
25.7
177.2
Table 4: South Crofty pre-production capital costs
The South Crofty underground mining operation is estimated to have a low total unit operating
cost, averaging US$103 per tonne of mineralised material, totalling US$611 million over the 14year LOM.
Mining
Mine
pumping
treatment
Processing
G&A
Closure cost
and
water
Unit Cost
(US$$/t)
Total LOM
Cost (US$M)
64.7
385.1
2.9
17.6
24.8
9.3
0.9
147.9
55.1
5.6
60
Total
102.6
611.3
Table 5: South Crofty operating costs
Average LOM net unit cash costs, inclusive of treatment charges and by-product credits from
copper and zinc are estimated to be US$12,705 per tonne of payable tin sold. The AISC is
estimated at US$13,661 per tonne, potentially positioning South Crofty within the first quartile of
the global tin industry cost curve.
Cash Flow Generation
South Crofty's estimated low operating costs and high margin tin sales are expected to support
strong after-tax free cash flow generation totalling approximately US$447 million across the
Project (US$626 million from start of production) and peaking at US$82 million in the second year
of
production.
Figure 9: South Crofty after-tax free cash flow profile
Opportunities and Upside Options
The PEA is based on the latest South Crofty MRE updated in late-2023 that produced a significant
increase in contained tin in the Indicated category of the lower mine (see 30 th October 2023 news
release). Additional in-mine exploration provides the opportunity to extend South Crofty's mine
life beyond the current 14-year LOM. In addition, near-mine exploration at targets such as the
Wide Formation provide further potential to add to the existing mineral resource base and the
scope to increase production rates.
Next Steps
During the remainder of 2024, the Company intends to continue with its published work
programme, including, as a top priority, the simultaneous dewatering of the mine and
refurbishment of New Cooks Kitchen Shaft.
Further technical work is also underway to advance the Project towards a Feasibility Study,
including detailed engineering of the processing plant. This work will inform discussions with
qualified local contractors and identify suppliers for long lead time items, in order to enable
timely execution of the project construction schedule once a construction decision is taken.
Qualified Persons
The Qualified Persons for the PEA are Mr Dominic Claridge, FAusIMM, Principal Mining Engineer
(AMC); Mr Nick Szebor, MCSM, CGeol, EurGeol, FGS, General Manager (Maidenhead, UK) and
Principal Geologist (AMC); Mr Mike Hallewell, FIMMM, FSAIMM, FMES, CEng (Independent
Consultant); Mr Barry Balding, PGeo, EurGeol, Technical Director - Mining Advisory Europe (SLR);
Ms Angela Collins, Dip BA MRTPI, Principal Planner (SLR); Mr Steve Wilson, ACSM, CEng, FIMMM,
Managing Director: Europe (P&C); and Dr Barrie O'Connell, ACSM, FIMMM, CEng (Independent
Consultant). Qualified Persons under National Instrument 43-101 (NI 43-101) and Competent
Persons as defined under the JORC Code (2012).
All QPs have reviewed the technical content of this news release for the South Crofty deposit and
have approved its dissemination.
A Technical Report disclosing the PEA in accordance with the requirements of NI 43-101 will be
prepared by AMC on behalf of Cornish Metals and filed on SEDAR within 45 days of this news
release. Messrs Claridge, Szebor, Hallewell, Balding, Wilson and O'Connell, and Ms Collins consent
to the inclusion in this announcement of the matters based on their information in the form and
context in which it appears.
This news release has been reviewed and approved by Mr Owen Mihalop, MCSM, BSc (Hons), MSc,
FGS, MIMMM, CEng, Chief Operating Officer for Cornish Metals Inc, who is the designated QP for
the Company.
ABOUT CORNISH METALS
Cornish Metals is a dual-listed mineral exploration and development company (AIM and TSX-V:
CUSN) focused on advancing the South Crofty high-grade, underground tin project through to a
construction decision, as well as exploring its additional mineral rights, located in Cornwall,
United Kingdom.
·
South Crofty is a historical, high-grade, underground tin mine that started production in 1592 and
continued operating until 1998 following over 400 years of continuous production;
·
The Project possesses Planning Permission for underground mining (valid to 2071), to construct new
processing facilities and all necessary site infrastructure, and an Environmental Permit to dewater the
mine;
·
South Crofty has one of the highest grade tin Mineral Resource globally and benefits from existing mine
infrastructure including multiple shafts that can be used for future operations;
· Tin is a Critical Mineral as defined by the UK, American, and Canadian governments;
· Approximately two-thirds of the tin mined today comes from China, Myanmar and Indonesia;
· There is no primary tin production in Europe or North America;
·
Tin connects almost all electronic and electrical infrastructure, making it critical to the energy transition responsible sourcing of critical minerals and security of supply are key factors in the energy transition and
technology growth;
· South Crofty benefits from strong local community, regional and national government support.
· Cornish Metals has a growing team of skilled people, local to Cornwall, and the Project could generate up to
320 direct jobs.
ON BEHALF OF THE BOARD OF DIRECTORS
"Kenneth A. Armstrong"
Kenneth A. Armstrong P.Geo.
Engage
with
us
directly
at
our
investor
hub.
Sign
up
at:
https://investors.cornishmetals.com/link/5PmYnP
For additional information please contact:
Cornish Metals
Fawzi Hanano
Irene Dorsman
investors@cornishmetals.com
info@cornishmetals.com
Tel: + 1 (604) 200 6664
SP Angel Corporate Finance
LLP
(Nominated Adviser & Joint
Broker)
Richard Morrison
Charlie Bouverat
Grant Barker
Tel: +44 203 470 0470
Cavendish Capital
Limited
(Joint Broker)
Derrick Lee
Neil McDonald
Leif Powis
Tel: +44 131 220 6939
Hannam & Partners
(Financial Adviser)
Matthew Hasson
Andrew Chubb
Jay Ashfield
cornish@hannam.partners
Tel: +44 207 907 8500
BlytheRay
(Financial PR)
Tim Blythe
Megan Ray
tim.blythe@blytheray.com
megan.ray@blytheray.com
Tel: +44 207 138 3204
Markets
Tel: +44 207 220 0500
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX
Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.
Caution regarding forward looking statements
This news release contains certain "forward-looking information" and "forward-looking statements" (collectively, "forwardlooking statements"). Forward-looking statements include predictions, projections, outlook, guidance, estimates and
forecasts and other statements regarding future plans, the realisation, cost, timing and extent of mineral resource or
mineral reserve estimates, estimation of commodity prices, currency exchange rate fluctuations